A seasonal plant may have utilities physically installed and still have limited availability during a shutdown or restart. Confirm which services will be running at the actual commissioning time and which teams can release them. Use the machine supplier’s documented demands and the site’s own measurements.
Separate installed capacity from the commissioning window
Ask the installer to confirm operating hours, connection positions and what other equipment shares each service. Include site staffing and if utility verification needs a separate visit. Assign unresolved measurements to a responsible person before agreeing to the first wet trial.
| Service | Supplier requirement | Available and approved when |
|---|---|---|
| Electrical supply and circuits | ___ | ___ |
| Compressed air and connections | ___ | ___ |
| Process water and drainage | ___ | ___ |
| Cooling and ancillary equipment | ___ | ___ |
For a winter installation, a refrigeration circuit may be physically connected while its circulation pump is unavailable until the contracted restart. Tie each utility commitment to a date, measurement point and responsible person. Schedule supported dry checks separately if the plant and supplier confirm that the wet trial must wait.
Read the local connection and utilities guide in German
Check site readiness in the relocation and acceptance guide
Discuss commissioning at your Austrian site
Share the location, commissioning dates, selected equipment and utilities still open.